| Disclosure law | None |
|---|---|
| UCC filing office | West Virginia Secretary of State, Business and Licensing Division (UCC Online Services) |
| State agencies pay | 45 days after a legitimate uncontested invoice is received, for purchases made on or after July 1, 2025; the receiving agency must process the invoice within 10 business days |
| Late-pay interest (state) | No interest for state agencies; a late agency must report the violation to the State Auditor, a vendor may report it too, and the Auditor publishes a monthly list of late agencies |
| Lien deadline (private) | Generally within 100 days after the subcontract is completed or after the claimant last furnished materials (§38-2-9, §38-2-10), recorded with the county clerk; claimants without a contract with the owner must also notify the owner within the same 100 days |
| Public payment bond | No dollar threshold in the statute: a bond is required on any contract to build, improve or repair a public building or structure, in a sum at least equal to the reasonable cost of materials, equipment and labor |
Who uses invoice factoring in West Virginia?
West Virginia receivables come from energy, chemicals, healthcare and a large federal footprint. Coal and Marcellus and Utica natural gas producers buy trucking, equipment repair, fabrication and oilfield services on account. The Kanawha Valley chemical corridor around Charleston and plants along the Ohio River pay industrial contractors and suppliers. Federal payers include the FBI Criminal Justice Information Services Division in Clarksburg, the NASA Independent Verification and Validation Facility in Fairmont and the Treasury Bureau of the Fiscal Service in Parkersburg, all of which use contractors. Hospital systems are among the largest buyers of staffing and services.
Payment timing depends on who the customer is. State agencies must pay within 45 days of a legitimate claim under the Prompt Payment Act of 2025 (effective July 8, 2025), but the law only requires late agencies to be reported to the State Auditor; it adds no interest. Counties and cities have 60 days and owe interest after that. Private construction has no prompt pay statute, so contract terms control, and subcontractors often wait on the owner's pay cycle.
- Industries that factor most: Coal mining and mining services, Natural gas production and pipeline services, Chemical manufacturing, Healthcare services, Federal contracting and IT services.
- Metro areas: Charleston, Huntington, Morgantown, Parkersburg, Wheeling.
- Federal installations that buy from local firms: FBI Criminal Justice Information Services Division (Clarksburg), NASA Independent Verification and Validation Facility (Fairmont), Bureau of the Fiscal Service (Parkersburg).
Does West Virginia regulate invoice factoring?
West Virginia has no commercial financing disclosure law, so a factor is not required by state law to give you a standardized cost disclosure. There is no federal one for business financing either. That puts the burden on you to get every fee in writing.
Factoring is generally structured as a purchase of your invoices rather than a loan, which is why consumer lending rules and usury caps generally do not apply to it. The protections that do apply come from your contract and from the Uniform Commercial Code, which governs the sale of accounts in every state.
Ask any provider for the total dollar cost on a sample invoice, the advance rate, every fee, the term and the exit terms. Our proposal checklist lists what a good proposal shows, and the disclosure law tracker shows which states require it.
How do UCC filings work in West Virginia?
Where UCC-1s are filed in West Virginia: West Virginia Secretary of State, Business and Licensing Division (UCC Online Services). Filings and searches are online only (paper filing ended in 2018, except for transmitting utilities and a few amendments); filing costs $20 plus a $3 portal fee, and a search costs $10 plus $1 a page plus a $3 portal fee.
A factor will search that index on your exact legal name before it funds, and will file its own UCC-1 on your accounts receivable at closing. Anyone already claiming your receivables, such as a bank, an SBA lender or a merchant cash advance provider, must release, subordinate or sign an intercreditor agreement first. Search your own name first at the official West Virginia UCC search; old filings from paid-off lenders are common and can take a week or more to terminate. More in UCC liens and intercreditor agreements.
How fast do government payers in West Virginia pay?
West Virginia state agency deadline (W. Va. Code §12-10-1 to §12-10-3 (Prompt Payment Act of 2025, HB 2152)): 45 days after a legitimate uncontested invoice is received, for purchases made on or after July 1, 2025; the receiving agency must process the invoice within 10 business days. Late interest: No interest for state agencies; a late agency must report the violation to the State Auditor, a vendor may report it too, and the Auditor publishes a monthly list of late agencies. Counties (W. Va. Code §7-5-7) and municipalities (§8-13-22d) must pay within 60 days of a legitimate uncontested invoice, with interest at the State Tax Commissioner's rate from day 61, unless unforeseen budget limits prevent payment.
Federal agencies follow the Prompt Payment Act: generally 30 days after a proper invoice, with interest at the Treasury rate (4.75% for July 1, 2026 to December 31, 2026) when they pay late. To factor federal invoices, the funder usually needs an assignment of claims acknowledged by the contracting officer, which adds a week or two to setup. See factoring for government contractors and the prompt payment interest calculator.
What do West Virginia lien and prompt pay rules mean for construction factoring?
Funders that factor construction receivables check lien and bond rights before they advance on a pay application, because those rights are what get an unpaid sub paid. Described generally:
- Mechanics lien deadline (private work, W. Va. Code §38-2-1 et seq.): Generally within 100 days after the subcontract is completed or after the claimant last furnished materials (§38-2-9, §38-2-10), recorded with the county clerk; claimants without a contract with the owner must also notify the owner within the same 100 days. To enforce: Suit in circuit court within 6 months after the lien notice is filed (§38-2-34).
- Preliminary notice: Not generally required; an optional notice to the owner under §38-2-20 is available.
- Private prompt pay: we could not verify a general private construction prompt payment law in West Virginia; your subcontract's pay terms control.
- Public projects (W. Va. Code §38-2-39): you cannot lien public property, so payment bonds take its place. Bond required: No dollar threshold in the statute: a bond is required on any contract to build, improve or repair a public building or structure, in a sum at least equal to the reasonable cost of materials, equipment and labor.
- Read every lien waiver before you sign it, and ask counsel how a waiver signed before payment affects your rights. More in factoring for construction subcontractors.
What else should a West Virginia business know?
- The Prompt Payment Act of 2025 covers state agency purchases of goods and services generally, not just construction, but carries no interest penalty, so late state payments do not grow.
- Public property cannot be liened in West Virginia; subcontractors and suppliers on public jobs look to the contractor's bond under §38-2-39, and its claim timing is set by the bond terms rather than the statute.
Questions people ask
Is invoice factoring legal in West Virginia?
Yes. Factoring is a sale of accounts receivable, and West Virginia treats it under its version of UCC Article 9 like other states do. The factor usually files a UCC-1 financing statement with the Secretary of State to perfect its interest. There is no state license or registration specific to commercial factoring, but the contract terms matter, so read the recourse, reserve and fee schedule closely.
Does West Virginia require a disclosure for factoring deals?
No. As of November 2026, West Virginia has not passed a commercial financing disclosure law like those in California, New York or Virginia. A factor does not have to give you a state form showing an APR or total cost. You should still ask for the full fee schedule in writing and compare offers on the effective cost per month.
Where do I search for UCC liens in West Virginia?
Use the Secretary of State's UCC Online Services at apps.wv.gov/sos/ucc. Since 2018 it is the only way to get a UCC search from the state. A search costs $10, plus $1 a page and a $3 portal fee. Run one on your own business before you factor, since a lender's blanket lien on receivables can block a new factor.
How fast does the State of West Virginia pay its vendors?
Under the Prompt Payment Act of 2025, state agencies must pay a legitimate uncontested invoice within 45 days of receipt, for purchases made on or after July 1, 2025. The law has no interest penalty; late agencies are reported to the State Auditor, which posts a monthly list. Counties and cities have 60 days and owe interest after that. Factoring can cover the wait.
How fast can a West Virginia business get funded by factoring?
With a clean file (current AR aging, invoices, a clear UCC search and creditworthy customers), first funding commonly takes about one to three weeks, and later invoices usually fund within a day or two of verification. Federal receivables take longer because of the assignment of claims.
Sources
- West Virginia Code §12-10-3, Prompt Payment Act of 2025
- Enrolled HB 2152 (2025), West Virginia Legislature
- West Virginia Code §7-5-7, county payment of invoices
- West Virginia Code §38-2-39, public building bonds
- West Virginia Secretary of State, UCC filing procedures
- Levelset, West Virginia mechanics lien FAQs
- Levelset, West Virginia prompt payment FAQs
- Venable, state commercial financing disclosure laws (March 2026)
General information, not legal advice. Statutes and deadlines change and have exceptions; check the source or ask counsel before relying on one. Spot an error? Tell us and we will fix it.